Advisory to our customers in Manila and Pasay

SERVICE IMPROVEMENT ADVISORY
Maynilad is conducting maintenance activities in Manila as part of its continuous effort to improve water services in the West Zone.
Duration: March 28, 2018 (WEDNESDAY) 3 p.m. to March 30, 2018 (FRIDAY) 2 a.m.
Activities:
1. Valve replacement at Ermita Pumping Station
2. Valve insertion at Quirino Avenue Ext. corner Plaza Dilao.
3. Flow meter installation along Estrada corner Espiritu Street and Labores Street
THIS PROJECT WILL TEMPORARILY INTERRUPT WATER SUPPLY IN THE FOLLOWING AREAS OF MANILA AND PASAY CITY:
MANILA
  • Ermita (659-A, 660-A, 659 to 661, 663, 664, 666 to 670)
  • Malate (696 to 701, 709, 713, 716, 717, 719, 726 to 734 and 744)
  • Paco (662, 671, 672, 674, 676 to 685, 821 to 832)
  • Sta. Mesa (587 to 625)
  • Pandacan (833 to 846, 847 to 868, 870-872)
  • Santa Ana (745-762)
PASAY
  • San Isidro (1 to 9, 14 to 23, 33 to 37, 41 to 48)
  • San Rafael (68 to 75, 80 to 92)
  • San Roque (97 to 100, 113 to 119, 136 to 143)
  • Sta. Clara (49 to 96, 101 to 112, 120 to 135)
Maynilad is advising customers in these areas to store enough water for the duration of the water service interruption.
* There might be a delay in the resumption of water service in your area. This is due to several factors such as your area’s elevation, its distance from our pumping stations, and the volume of withdrawal from our mainlines.

Leave a Comment